Solar roofing
Re-roof and array in one mobilisation, so you never pay to remove and reinstall panels.
- SpecificationArchitectural shingle or standing seam · single mobilisation
How we scope it
Removing and reinstalling an existing array so a roof can be replaced is a real cost, typically several thousand dollars for a residential system, and it buys you nothing. If the shingles have fewer than ten years of service left, replacing them before the array goes on is simply cheaper over the life of the system.
We schedule the roof and the array as one job. The roofing crew strips, re-decks where the sheathing is soft, dries in, and lays new shingles. The solar crew follows the same week and lands mounts directly on rafters through fresh underlayment with proper flashings, rather than chasing old penetrations.
On standing seam metal there is no penetration at all. Clamps grip the seam and the rails sit on top, which is the cleanest and longest lived mounting we install.
Scope
What is included
Six deliverables, written the way they appear on the contract rather than the way they appear in a brochure.
Deck inspection
Sheathing checked for soft spots and nail pull once the old covering is off, with replacement priced per sheet.
New underlayment
Synthetic underlayment across the field and self adhered membrane in the valleys and at the eaves.
Roof covering
Architectural asphalt shingle or standing seam metal, matched to your structure and your budget.
Rafter located mounts
Every mount found with a stud finder and confirmed by the lag pull, then flashed under the course above.
Single warranty conversation
Roof and array from one contractor, so nobody points at anyone else when a leak appears.
Array install
Rails, modules, rapid shutdown and conduit, completed within days of the roof going on.
Sequence
How the work runs
- 1
Roof assessment
Remaining shingle life, deck condition, ventilation and any existing leak history recorded.
- 2
Combined proposal
One price covering both scopes, with the array design already accounting for the new roof planes.
- 3
Tear off and dry in
Old covering stripped, deck repaired, underlayment down the same day it is opened.
- 4
New roof
Shingles or panels laid, ridge vent set, penetrations flashed.
- 5
Array
Mounts, rails, modules and electrical, then inspection and PTO as for any install.
Pricing factors
What moves the number
We do not publish a single price for this scope because these five variables change it substantially. Here is what each one does.
How people pay for it| Factor | Typical range | Effect |
|---|---|---|
| Roof area | 1,500 to 4,000 sq ft | Priced per square, as with any roofing job |
| Covering | Asphalt or standing seam | Metal costs more up front and outlives two shingle roofs |
| Deck condition | Sound to significant repair | Unknown until the old covering comes off, so it is priced per sheet |
| Pitch and stories | 4:12 to 12:12 | Steep and high roofs need more fall protection and more labour |
| Penetrations | Few to many | Plumbing vents, chimneys and skylights all cost flashing detail and array area |
Questions
Solar roofing: common questions
Usually yes. An architectural shingle roof runs 20 to 25 years here. Twelve years in leaves under half its life, and the array will still be producing long after the shingles fail.
The opposite, mostly. Shingles under modules see less ultraviolet and less thermal cycling. The risk is bad flashing, not the panels themselves.
Standing seam is the best surface we work on. Clamps grip the seam, no holes, fast install, and the roof outlives the modules.
Yes. Skylights cost array area and need their own flashing detail, both of which we account for in the layout before you sign.
Next
Usually bought alongside
Residential solar
Rooftop arrays from 5 kW to 14 kW DC, designed around your last twelve utility bills.
OpenBlower door · thermal imaging · duct leakageEnergy audits
Blower door and thermal survey that often cuts the array you need before you buy it.
OpenPer module telemetry · annual service · 48 hour responseMonitoring and maintenance
Module level production alerting and a scheduled service programme that catches faults early.
Open
Start with the numbers, not a sales visit
Send twelve months of kWh and a roof photo. You get a sized system, a production model and a payback figure before anyone comes out.
No pressure appointment. The site check is free and the design is yours to keep.